| back to Schedule page |
| AYLP 2011-2012 Schedule |
| |
Orientation: |
Monday September 5, 2011 |
| |
At Delhi: |
Hindi , Urdu and Punjabi |
| |
At the respective Language Centers: |
All other LPs |
| |
Arrival of students at respective LP Centers and visit to the host families |
Tuesday, September 6, 2011 |
| |
Move to chosen families and proficiency test |
Wednesday, September 7, 2011 |
| |
Opening Bank account, Registration etc. |
Thursday, September 8, 2011 |
| |
|
|
| |
Regular classes Commence: |
Friday, September 9, 2011 |
| |
I Mid Semester Break: |
Wednesday, October 12, to Sunday, October 16, 2011 (both days inclusive) |
| |
Classes resume: |
Monday, October 17 , 2011 |
| |
Midterm Evaluation: |
Monday, December 12, 2011 |
| |
|
|
| |
Christmas Break: |
Saturday, December 17, 2011 to Sunday, January 8, 2012 |
| |
Classes resume: |
Monday, January 9, 2012 |
| |
|
|
| |
II Mid Semester Break: |
Wednesday February 22, 2012 to Sunday, February 26, 2012 (both days inclusive) |
| |
Classes resume: |
Monday, Feb 27, 2012 |
| |
Final Evaluation: |
Monday, April 23, 2012 |
| |
Final test and Project presentation: |
Thursday, April 26, 2012 |
| |
Program Conclusion and farewell: |
Monday , April 30, 2012 |
| |
| AYLP 2010-2011 Schedule |
| |
Orientation: |
Monday September 6, 2010 |
| |
At Delhi: |
Hindi & Urdu |
| |
At the respective Language Centers: |
All other LPs |
| |
Regular classes Commence: |
Wednesday, September 8, 2010 |
| |
|
|
| |
I Mid Semester Break: |
Wednesday, October 13, to Sunday, October 17, 2010 (both days inclusive) |
| |
Classes resume: |
Monday, October 18 , 2010 |
| |
Midterm Evaluation: |
Monday, December 13, 2010 |
| |
|
|
| |
Christmas Break: |
Saturday, December 18, 2010 to Wednesday, January 5, 2011 |
| |
Classes resume: |
Thursday, January 6, 2011 |
| |
|
|
| |
II Mid Semester Break: |
Wednesday February 23, 2011 to Sunday, February 27, 2011 (both days inclusive) |
| |
Classes resume: |
Monday, Feb 28, 2011 |
| |
Final Evaluation: |
Monday, April 25, 2011 |
| |
Final test and Project presentation: |
Wednesday, April 27, 2010 |
| |
Program Conclusion and farewell: |
Friday , April 29, 2011 |
|
|
|
|
|